| Service name: |
Diversion of Cable Lines (after applying for clearance and receiving the non-clear certificate)
|
| Service description: |
Transfer of lane for electricity lines (service can be provided to empty plots prior to construction) |
| Process description: |
- Submitting application for cable lines diversion.
- Obtaining an appointment for inspection.
- Completion of site inspection & approval from concerned parties.
- Notifying client of required fees.
- Commencing of work on transfer of lane for electricity lines.
|
| Fees: |
| Payable for | Amount Dhs | Fees |
| TAQA Distribution |
unspecified |
Cost verified based on cables and equipments to be diverted with supervision charges |
|
| Service access: |
Service Inquiry: TAQA Distribution Contact Center (800 2332) 24 Hours / 7 days Applying for Service: Technical counter , Al Saad Branch, Al Hayar Branch and Al Wagan Branch |
| Working hours: |
Technical counter & external branches during official working hours (7AM – 3 PM) from Sunday to Thursday |
| Service Availability: |
Individuals & Corporate |
| Required Documents |
Copy of site plan Site inspection report |
| Service Duration : |
5 Working Days |