New Water Connection


Service name:

New Water Connection

Service description: Linkage of premises with water connection/connection of water service for new premises
Process description: Submission of application with required documents for water connection.
Obtaining appointment for inspection.
Completion of inspection & approving plans from concerned department.
Informing client for payment of required fees.
Commencing work on water line connection.
Special conditions: Electricity service must be connected before water connection.
Water connection size varied based on family members.
Fees:
Payable for Amount DhsFee
Al-Ain Distribution Company  unspecified Cost of water connection verified based on connection size & length of line after completing all the procedures
Service access: Service Inquiry:
AADC Contact Center (8009008) 24 Hours / 7 days Applying for Service:
Technical counter , Al Saad Branch, Al Hayar Branch and Al Wagan Branch   
Working hours: Technical counter & external branches during official working hours (7AM – 3 PM) from Sunday to Thursday
Service Availability: Individuals & Corporate
Service Duration : 45 Days

Required documents:

Documents / kind PremisesCommercialGovernmentalTemporary sites
Letter from corporation / company / Authority        
Copy of Owner's nationality entry        
House Maids Visas' Copy (If Exists)        
Copy of site plan        
Copy of trade license        
Approval for tank location        
Account No.